Tarlton v. Miller’s of Claflin, Inc. and S & H Lumber Co. and Kustom Floor Designs, et al.

View PDFPDF icon linkimg description
  • Status Published
  • Release Date
  • Court Court of Appeals
  • PDF 101968
No. 101,968

IN THE COURT OF APPEALS OF THE STATE OF KANSAS

KRIS T. TARLTON AND SARA L. TARLTON,
Appellees,

v.

MILLER'S OF CLAFLIN, INC., AND S & H LUMBER CO., INC.,
Appellants,

and

KUSTOM FLOOR DESIGNS, et al.,
Defendants.


SYLLABUS BY THE COURT

1.
In an appeal following a bench trial in which the evidence consisted only of
documents and the district court was not required to consider matters of credibility but
rather to rule on the documentary evidence before it, an appellate court is equally capable
of examining the documents to determine the proper disposition of the case. Accordingly,
under these circumstances, appellate review is de novo.

2.
Mechanics' liens are governed by K.S.A. 60-1101 et seq. They are designed to
protect unpaid suppliers of labor and materials for real estate construction projects.
However, to create a lien a claimant must strictly comply with the applicable statute. One
claiming a mechanic's lien has the burden of bringing one's self clearly within the
provisions of the statute.
1

3.
There are different lien perfection requirements for general contractors and for
subcontractors. One difference is the requirement in K.S.A. 60-1103a(b) that
subcontractors mail to the property owner the warning statement identified in K.S.A. 60-
1103a(c) or obtain the owner's signed acknowledgement of that warning and file an
affidavit stating that they did so.

4.
Whether a contract exists is a question of fact.

5.
The issue of who has the burden of proof in resolving the validity of mechanics'
liens is examined. Under the facts presented, the mechanic's lien claimants had the
burden to prove the validity of their liens, which turned upon the claimants proving they
contracted with the owners to supply labor and materials to the project, rather than being
subcontractors of the owners' general contractor.

6.
When agency is at issue, the party claiming the existence of an agency relationship
has the burden of establishing its existence.

Appeal from Barton District Court; MIKE KEELEY, judge. Opinion filed April 2, 2010. Affirmed.

Jeff Lee McVey, of McPherson & McVey Law Offices, Chtd., of Great Bend, for appellants.

Kenneth L. Kerns, of Great Bend, for appellees.
2

Before MCANANY, P.J., GREEN and MALONE, JJ.

MCANANY, J.: Miller's of Claflin, Inc. (Miller), and S & H Lumber Co. (S&H),
appeal the district court's cancellation of their claimed mechanics' liens on the home of
Kris and Sara Tarlton (Tarltons) based upon the finding that Miller and S&H failed to
properly perfect their liens as subcontractors.

Facts

The Tarltons engaged Chad Gisick, d/b/a Gisick Construction, to serve as the
general contractor in the construction of their new home. They made periodic progress
payments to Gisick for work done on the project, apparently based on representations
from Gisick but without obtaining lien waivers from the various suppliers. The payment
schedule left a remaining balance to be paid to Gisick upon completion of the project.
Gisick died in February 2007 before completing the project. His estate was unable to
satisfy the outstanding claims of his subcontractors. Miller and S&H filed mechanic's lien
statements for unpaid work and materials. Neither Miller nor S&H sent the Tarltons the
warning statements required of subcontractors pursuant to K.S.A. 60-1103a(b).

Following Gisick's death, the Tarltons filed an interpleader action with respect to
the remaining unspent funds for the project. S&H and Miller counterclaimed for
enforcement of their mechanics' liens. The Tarltons ultimately moved the court for
adjudication and cancellation of the liens claimed by Miller and S&H.

The district court tried the issue based upon the documentary evidence supplied by
the parties, the oral arguments of counsel, and the arguments in their briefs. The court
3
ruled after reviewing "the pleadings . . . as well as the attachments which includes
exhibits and affidavits." There are no affidavits in the record relating to the central issue
in this appeal: whether S&H and Miller had contracts with the Tarltons to supply labor
and materials to the project. The court ruled that S&H and Miller were subcontractors of
Gisick who failed to perfect their liens as subcontractors by giving the statutorily required
notice to the owners. Thus, the court struck down their liens. S&H and Miller appeal.

Standard of Review

Under these circumstances, in which the district court was not required to consider
matters of credibility but rather to rule on the documentary evidence before it, we are
equally capable of examining the documents to determine if the liens were properly
perfected. Accordingly, our review is de novo. See Double M Constr. v. Kansas
Corporation Comm'n, 288 Kan. 268, 271, 202 P.3d 7 (2009).

Mechanics' Liens

Mechanics' liens are governed by K.S.A. 60-1101 et seq. They are designed to
protect unpaid suppliers of labor and materials for real estate construction projects. See
K.S.A. 60-1101. However, to create a lien a claimant must strictly comply with the
applicable statute. Buchanan v. Overley, 39 Kan. App. 2d 171, 175, 178 P.3d 53 (2008).
One claiming a mechanic's lien has the burden of bringing one's self clearly within the
provisions of the statute. Creme de la Crème of Kansas, Inc. v. R & R Int'l, Inc., 32 Kan.
App. 2d 490, 493, 85 P.3d 205, rev. denied 278 Kan. 844 (2004).

There are different lien perfection requirements for general contractors and for
subcontractors. See generally Stewart v. Cunningham, 219 Kan. 374, 376, 548 P.2d 740
4
(1976). One difference is the requirement in K.S.A. 60-1103a(b) that subcontractors mail
to the property owner the warning statement identified in K.S.A. 60-1103a(c) or obtain
the owner's signed acknowledgement of that warning and file an affidavit stating that
they did so.

There is no question that Miller and S&H did not comply with the statutory
requirement that subcontractors give the owners this warning statement. The case turns
on whether Miller and S&H were subcontractors of Gisick, the general contractor, or
whether they had independent, direct contracts with the Tarltons to supply materials and
labor to the project. Whether contracts existed between the Tarltons and these claimants
are questions of fact. See In re Estate of Hjersted, 285 Kan. 559, 589, 175 P.3d 810
(2008). Applying the de novo standard of review, we must examine the documentary
evidence before the district court to determine if the party bearing the burden of proof on
the issue of the existence of a contract between the parties met that burden.

Burden of Proof

First, we must determine who has the burden of proof on the issue of the status of
Miller and S&H vis-a-vis the Tarltons. We find no Kansas authority that addresses the
issue in the context of the facts now before us. However, the issue arises from time to
time in declaratory judgment actions in which courts have developed an analytical
framework for deciding which party bears the burden of proof.

Fireman's Fund Ins. Co. v. Videfreeze Corp., 540 F.2d 1171 (3d Cir. 1976), cert.
denied 429 U.S. 1053 (1977), presents a thoughtful analysis of the issue. In Videfreeze,
the court noted the following tests for determining who has the burden of proof in a
declaratory judgment action:
5

"(1) whether the plaintiff objected to assuming the burden of proof; (2) which party
asserted the affirmative of the issue; (3) which party would lose in the absence of any
evidence on the issue; (4) what sort of relief is sought." 540 F.2d at 1175.

In Videfreeze, the insureds suffered a loss when a rockslide damaged their
building and interrupted their business in St. Thomas, Virgin Islands. The insurer had
issued a policy containing an endorsement that provided coverage for losses caused by
earthquake. The insureds made a claim under the policy, asserting that the rockslide was
caused by an earthquake which four witnesses claimed to have felt, though no earthquake
was recorded on the nearest seismograph in Puerto Rico. The insurer denied that an
earthquake caused the rockslide, claiming that rain water penetrated fractures in the rock
above the insured's building and dislodged the side of the cliff, causing the rockslide. The
insurer brought a declaratory judgment action to determine the rights and responsibilities
of the parties under the policy.

Central to resolution of the dispute was determining who had the burden of proof.
The court cited Traveler's Ins. Co. v. Greenough, 88 N.H. 391, 190 A. 129 (1937), in
which "the New Hampshire Supreme Court refused to displace the burden of proof of
coverage from its normal location on the insured, despite the reversed positions of the
parties in the action." Videfreeze, 540 F.2d at 1175. The court noted that when an insurer
sues its insured to obtain a declaration that there is no coverage under the policy, "'(i)t
would seem rather anomalous that so important a matter (as the burden of proof) should
depend on the chance of who first sues . . . .' [Citation omitted.]" 540 F.2d at 1176.

The Videfreeze court also cited Reliance Life Ins. Co. v. Burgess, 112 F.2d 234
(8th Cir.), cert. denied 311 U.S. 699 (1950), and observed:
6

"In Burgess, the insurance company was made to bear the burden of proof but not
merely because it happened to be the plaintiff in the declaratory judgment action. Rather,
the court considered that the company disputed coverage by asserting an affirmative
defense of exclusion and that the insured neither asked for affirmative relief nor put forth
a cause of action. In that posture, the insurer properly was required to prove that the loss
was due to an excluded cause." Videfreeze, 540 F.2d at 1175.

The insureds in Videfreeze asserted a counterclaim for coverage. "[T]he insureds,
although nominally the defendants, were affirmatively asserting coverage under the
policies and risked an adverse judgment on their counterclaims for damages if they
adduced no evidence of coverage." 540 F.2d at 1176. Accordingly, the court found that
the insureds bore the burden of proof on the issue of coverage.

For a similar analysis, see Preferred Acc. Ins. Co. of N.Y. v. Grasso, 186 F.2d 987,
991 (2d Cir. 1951).

Turning to the claims now before us, we first examine the procedural history. The
Tarltons brought this interpleader action against a number of suppliers on the project.
They claimed in their petition that S&H and Miller "have or may have claims." The
Tarltons tendered into court $13,389.17, "the amount remaining for distribution and
payment to the Defendants now making claims." The Tarltons did not ask for affirmative
relief with respect to the lien claims of S&H and Miller.

S&H and Miller answered and asserted a counterclaim, alleging that the Tarltons
entered into contracts with them to supply labor and materials on the project. They asked
the court to determine that their liens are valid liens on the property. The Tarltons filed
their reply, in which they denied the allegation that a contractual relationship existed
7
between them and S&H and Miller.

In due course the Tarltons filed their motion for adjudication and cancellation of
liens. They asserted that the lien statements filed by S&H and Miller failed to comply
with the statutory requirements and, therefore, the claimed liens were invalid. In their
response to the motion, S&H and Miller acknowledged the duty of subcontractors to
provide the warning statement described in K.S.A. 60-1103a, but asserted that they were
direct contracting parties with the Tarltons and not subcontractors of Gisick, the general
contractor.

Though the Tarltons initiated this interpleader action, they do not have the burden
of proof on the issue of whether a contract existed between them and S&H or Miller. The
issue was raised by S&H and Miller in their counterclaim. They have the burden of
bringing themselves within the aegis of our mechanic's lien laws. Their lien claims are at
risk if they cannot establish what they claimed in their counterclaim: that they are not
subcontractors of Gisick but direct contracting parties with the Tarltons. Accordingly,
they have the burden of proof on the claim that they had contractual relationships with
the Tarltons.

S&H's Lien Claim

With respect to S&H's lien claim, the district court found:

"There were at least eight separate documents with different dates wherein [S&H] sold
materials to Gisick Construction, who then provided the materials to the plaintiff. . . .
Even though [S&H] attempts at this time to claim Gisick was only an agent of the
[Tarltons], the documents make it clear Gisick was the contractor and [S&H] was the
8
sub-contractor. . . . There was no warning statement sent, and therefore, the lien is
defective and . . . must be cancelled."

The documents before the court clearly indicated that S&H was a subcontractor of
Gisick. Each of the invoices that S&H relies on contains the statement: "Sold To Gisick
Const." Nevertheless, S&H maintains on appeal that the Tarltons entered into an oral
contract with Gisick, who was the Tarltons' agent for supplying materials for the project.
There is no evidence that Gisick was the Tarltons' agent. He contracted to build a home
for them, not to serve as their agent. "[W]here the relationship of principal and agent is in
issue, the party relying on an alleged agency relationship has the burden of establishing
its existence by clear and satisfactory evidence." Town Center Shopping Center v.
Premier Mortgage Funding, Inc., 37 Kan. App. 2d 1, 6, 148 P.3d 565 (2006).

There is a total lack of evidence to support the existence of a contractual
relationship between S&H and the Tarltons. S&H failed to meet its burden of proof on
this issue. The district court did not err in finding S&H's lien claim to be invalid.

Miller's Lien Claim

The evidence supporting Miller's lien claim consists of two documents attached to
Miller's lien statement: an invoice and a sales order form. These two documents are the
entirety of the documentary evidence bearing on the issue of Miller's relationship to the
Tarltons. The invoice was generated from information contained on the sales order form.
Thus, we must look to the sales order form for evidence of the claimed contractual
relationship.

9
The sales order form lists "Chris and Sara Tarlton" as the customer. However, the
"Special Instructions" portion states: "Send to Chad." This apparently refers to Chad
Gisick, the general contractor. Send what to Chad and at what location? Clearly not the
purchased items of carpet, laminate, and tile. There would be no reason to deliver these
items to the general contractor rather than to the job site. After all, Miller was responsible
for installation of at least part of the materials, and the flooring in particular. There would
be no reason to send these materials to Gisick rather than to the job site. However, if this
reference on the document means that the materials should be sent to Gisick, that would
tend to prove that Gisick was the contracting party, not the Tarltons.

On the other hand, "Send to Chad" may refer to this sales order form itself, not the
materials being sold. If that is the case, then this would also tend to prove that Gisick was
the contracting party. Otherwise, why would Gisick have any interest in what particular
flooring and tile the Tarltons selected or what they agreed to pay for it?

A notation on the bottom of the sales order form suggests the latter alternative.
The form states: "Miller's make no express warranties. We honor and follow factory
warranties only. Orders are noncancelable upon manufacturer's acceptance. Please review
policies on reverse side of your ticket. Accepted By: X Phone (Chad Gisick)." We find
no explanation in the evidence why Miller would obtain Gisick's acceptance of the order
if the Tarltons were the contracting parties.

Miller had the duty to come forward with evidence from which one could
conclude that it is more probably true than not that the Tarltons were the contracting
party, not Gisick. From what meager evidence was provided, we cannot say that Miller
met its burden of proof. Because the adequacy of Miller's lien statement turns upon
Miller establishing that Miller had a direct contract with the Tarltons, we conclude that
10
11
the district court did not err in finding Miller's lien statement to be inadequate and its
claimed lien invalid.

Affirmed.
 